News of 2025

News Release
May 14, 2025

Receipt of Order by Corporate Group of Which METAWATER is a Participant for "Urasoe City New Clean Center Facility Construction and Operation Project" (tentative name)

Overview of construction

1. Construction name

Urasoe City New Clean Center Facility Construction and Operation Project (tentative name)

2. Location

1-555-25 Inanse, Urasoe City, Okinawa

3. Contractor

Representative company: JFE Engineering Co., Ltd.

Constituent members: METAWATER Co., Ltd.,Okinawa Plant Kogyo Company, Inc., Fukuyama Shoji Co., Ltd.

Cooperating companies: Rinkai Nissan Construction Co., Ltd., Agarie Kensetsu Co.,Ltd., Taisei Home Co., Ltd., Kyudenko Corporation, JFE Environmental Service Corporation, Konan Shisetsu Kanri Co., Ltd.

4. Project period

Project period: April 2025 to March 2029

Operation period: April 2029 to March 2049

5. Contract amount

45,650,000,000 yen (including tax)

6. Project Method

Design, Build and Operate (DBO)

7. Overview of facility and project

・Design and construction of energy recovery type waste disposal and treatment facility (stoker type 90t/day × 2 furnaces)

・Design and construction of material recycling promotion facility (14t/5h/day)

・Facility operation business for 20 years